Summary
The county approved road closures and surface improvement agreements with Clear Fork Creek Solar LLC for County Road 482. The developer will reimburse the county up to $46,355 for road materials while Precinct 4 provides labor and equipment.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 13, 2026.
Impact analysis
Developer will reimburse Wilson County up to $46,355 for road improvement costs.
Local solar energy development and county residents using improved road surfaces.
Drivers experiencing temporary road closures of up to 14 days on County Road 482.
Mentions & discussions (2)
Commissioners Court — Regular Meeting — 2026-04-13
The court discussed previously tabled road closure and improvement agreements tied to the Clear Fork Creek Solar project, taking no action.
Commissioners Court — Regular Meeting — 2026-03-23
The county approved road closures and surface improvement agreements with Clear Fork Creek Solar LLC for County Road 482. The developer will reimburse the county up to $46,355 for road materials while Precinct 4 provides labor and equipment.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Wilson County
What the council decided, in plain English — one email a week.
Join 569 residents following their cities
Free. Unsubscribe with one click any time. We never sell your email.